Planning Chair Orders Around Chinese New Year
Published by Foshanchair · Production planning desk in Foshan, China
Every year the same container misses the same vessel for the same reason: the buyer planned around the holiday dates printed in the news, and the factory planned around the three weeks before them. In 2027 the holiday itself starts on 5 February, with New Year’s Day falling on Saturday 6 February, so the official break runs long. None of that is when the wooden chair line actually stops. This is the calendar we work to when we schedule a chair programme for export.
1. Three shutdowns, not one date
The official holiday is only the middle layer. Above it sits the sales office, which closes on the published date. Below it sits the packing line, which stops when the last export container is loaded, usually one to two weeks earlier. Below that sit the machining, sanding and upholstery lines, which lose people from the second week of January as workers from Guangxi, Hunan and Sichuan leave to beat the ticket rush. A plant that quotes 30,000 pieces a month in October does not have 30,000 pieces of capacity in the second week of January; it has whatever the remaining crew can finish. Ask each supplier for their own last production day, their last loading day and their restart day in writing, and ask the same question of their finishers, foam cutters and hardware suppliers, because a chair cannot ship without the smallest component. Our factory and team publish those dates to customers every November.
2. Work backwards from the vessel, not from the holiday
The useful number is not “when does the factory close” but “when must the container sail to reach my warehouse on time”. Take a container that has to leave before the 2027 break: vessel ETD early January, container loading and trucking to Nansha or Yantian three to five days before that, pre-shipment inspection one to two days before loading, packing three to four days, and 25 to 30 days of production for a finished wooden or upholstered chair. The PO therefore has to be released in the first days of December, with the approved sample and the material order already behind it. Move one link and the whole chain moves, which is why a confirmed order placed in the third week of December usually ships in March rather than January. If your programme also needs tooling or a new frame, custom development has to start in the autumn, not after the autumn trade fairs.
3. Materials close before the factory does
Component lead times stretch in the same weeks, and they stretch unevenly. Fabric mills stop dyeing earlier than chair factories stop sewing, so a cover chosen in January may be quoted on a lot that no longer exists in February; ask for the mill’s last dye date, not the fabric supplier’s. Buyer-supplied material is the worst case, because ocean freight from Europe or Turkey adds five to six weeks before the fabric even reaches Foshan — COM rolls for a January run have to be booked in November. Foam, powder coating and hardware are local, but the suppliers behind them close a week before their customers do. Lumber needs kiln time, so a frame in a new species is a Q4 decision, as we set out in the notes on lumber grades and frame yield.
4. Space, rates and rolled bookings
Freight is where the calendar turns into money. The three weeks before the holiday are the tightest of the year on China–Europe and China–US lanes: rates climb, container availability tightens, and bookings confirmed at a low rate are the first to be rolled when a vessel is overbooked. Book three to four weeks ahead, insist on a named vessel and a booking number rather than a verbal “space is fine”, and confirm the documentation cutoffs at the same time, because a late bill of lading instruction can cost the sailing even when the container is loaded. Shipping in the quieter weeks of December is often cheaper overall than paying January peak rates, especially for heavy commercial restaurant chairs that cube out a container quickly. A rolled booking is also the most common reason a buyer believes the factory was late when the factory was finished on time.
5. The restart is a curve, not a switch
Production does not return on the first working day. Workers travel back over the following week or two, some do not return at all, and the lines are refilled with new hires who have never sanded that particular seat shape. Output in the first week back is typically half of normal, and the defect rate in the first two weeks is the highest of the year. Two controls protect the order: hold a first-article inspection on the first 50 pieces of the new run against the golden sample, and write the approval into the schedule instead of assuming it. A bar stool with a welded footrest, like our solid wood bar stool, is a good example: the frame is unchanged, but a new welder moves the footrest a few millimetres and nobody notices until the stools sit at the counter. Expect full speed by the second half of March, and build that into promises you make to your own customers.
6. What to write into the purchase order
Dates in a PO are only useful as milestones: PO release, material in house, production start, inspection date, ETD. Add a capacity reservation clause with a deposit paid before mid-December, because capacity in January is allocated to whoever has paid, not to whoever enquired first. Check the validity of any letter of credit against the realistic shipment window rather than the optimistic one, and extend the latest shipment date by at least fifteen days if the goods must sail after the restart. Name the holiday window explicitly in the delay clause instead of relying on generic force majeure, which many contracts exclude for predictable events. For large rollouts, split the order: a first shipment in December against a later one in March spreads both the freight risk and the quality risk, an approach that pairs well with the mechanics in changing a chair order after the PO. And book the third-party inspector early — inspection firms fill their January calendars in November, and a stackable wooden chair programme that cannot be inspected cannot be loaded.
Conclusion
The holiday is a fixed date; the loss of capacity around it is not, and that is the part that costs money. Three things make the difference: written last-day and restart dates from every supplier in the chain, a schedule built backwards from the vessel, and a PO that treats December capacity as something to reserve rather than something to request. If you are planning a chair order for delivery in the first quarter and want the dates mapped against our January loading schedule, send us the quantities and the target port and we will tell you which side of the holiday it realistically falls on.